Magna Mining (NICU.V): Exploration Update for the Shakespeare Ni-Cu-PGM Project, Ontario, Canada
Sudbury, Ontario–(Newsfile Corp. – August 17, 2021) – Magna Mining Inc. (TSXV: NICU) (“Magna” or the “Company”) is pleased to provide the following update on exploration activities at the Shakespeare Nickel-Copper-PGM Project.
The exploration drilling program is well advanced, with 5,203 meters drilled to date from a planned program of 9,000 meters. Numerous assay results are pending due to severe delays in assay turnaround times.
“Although receipts of assay results are well behind our expectations, we are encouraged by our visual assessments of the drill core,” said Mynyr Hoxha, Vice President of Exploration.
The objective of the current drill program at the Shakespeare Mine is to expand near surface resources and test footwall resource expansion targets around the S-13 Zone. At the Shakespeare Mine, 3,726 metres of drilling in 14 holes (plus one deepened hole) have been completed to date (see Figure 1).
Figure 1: Longitudinal section showing 2021 drill traces and pierce points
To view an enhanced version of Figure 1, please visit:
https://orders.newsfilecorp.com/files/8002/93334_1ed1cfbfd4508850_002full.jpg
There have been 2,228 samples sent to the assay lab for analysis and to date only 426 received, leaving 1,802 outstanding. This includes ~900 samples which are over 40 days since submission (see Table 1). This issue has been discussed with senior management at the assay provider and attributed to a high turnover in assay lab staff. Steps have been taken to ensure better turn-around-times going forward.
Table 1: List of outstanding samples
Hole ID | Samples Submitted | Outstanding Samples |
MMC-21-18 | 298 | 298 |
MMC-21-19 | 66 | 66 |
MMC-21-20 | 58 | 58 |
MSP-21-01 | 93 | 93 |
MSP-21-02 | 144 | 144 |
MSP-21-03 | 70 | 70 |
MSP-21-04 | 160 | 160 |
MMC-21-21 | 304 | 304 |
MMC-21-22 | 146 | 146 |
MMC-21-23 | 9 | 9 |
MMC-21-24 | 126 | 126 |
MMC-21-25 | 135 | 135 |
MMC-21-26 | 101 | 101 |
MMC-21-27 | 92 | 92 |
Total | 1802 | 1802 |
Borehole Electro Magnetic (BHEM) surveys conducted at Shakespeare in June will be repeated over the next two weeks. The objective of the planned BHEM survey is to further refine drill targets in the area of the previously identified large gravity anomaly in the footwall of the Shakespeare deposit (the “Birds Bane Anomaly”). The results of the BHEM survey will be used to design follow up drilling which management aims to complete in Q3.
Regional exploration drilling has also been conducted, including 873 metres in 4 holes at the Springer Pit Copper-Gold targets, located approximately 5-kilometers south-east of the Shakespeare deposit. Samples were submitted for assaying in June and July, and results are pending (see Figure 2).
Figure 2: Map displaying geology and hole traces from 2021 drilling on the Springer Target
To view an enhanced version of Figure 2, please visit:
https://orders.newsfilecorp.com/files/8002/93334_1ed1cfbfd4508850_003full.jpg
At the P-4 Nickel-Copper-PGM target, one hole has been drilled and one is on-going, for a total of 604 metres. P-4 is a highly prospective target, located approximately 5-kilometers on trend with the Shakespeare geological system (see Figure 3). The samples from P-4 will be sent to a different assay lab and assay results are anticipated within 4 weeks.
Figure 3: Map of regional magnetics showing relationship of the P-4 target and Shakespeare Mine site
To view an enhanced version of Figure 3, please visit:
https://orders.newsfilecorp.com/files/8002/93334_1ed1cfbfd4508850_004full.jpg
3,800-metres of diamond drilling remains to be completed over the next 6-8 weeks and Magna looks forward to being able to provide both the assay results and BHEM survey results as they become available.
Qualified Person
The technical information in this press release has been reviewed and approved by Mynyr Hoxha, Ph.D., P.Geo., the Company’s Vice President of Exploration. Dr. Hoxha is a qualified person under Canadian National Instrument 43-101.
About Magna Mining Inc.
Magna Mining is an exploration and development company focused on sulphide nickel, copper and PGM projects in the Sudbury Region of Ontario, Canada. The Company’s flagship asset is the past producing Shakespeare Mine which has major permits for the construction of a 4500 tonne per day open pit mine, processing plant and tailings storage facility and is surrounded by a contiguous 180km2 prospective land package. Additional information about the Company is available on SEDAR (www.sedar.com) and on the Company’s website (www.magnamining.com).
For further information, please contact:
Jason Jessup
Chief Executive Officer
or
Paul Fowler, CFA
Senior Vice President
Email: [email protected]
Cautionary Statement
This press release contains certain forward-looking information or forward-looking statements as defined in applicable securities laws. Forward-looking statements are not historical facts and are subject to several risks and uncertainties beyond the Company’s control, including statements regarding plans to complete exploration programs, potential mineralization, exploration results and statements regarding beliefs, plans, expectations or intentions of the Company. Resource exploration and development is highly speculative, characterized by several significant risks, which even a combination of careful evaluation, experience and knowledge may not eliminate. All forward-looking statements herein are qualified by this cautionary statement. Accordingly, readers should not place undue reliance on forward-looking statements. The Company undertakes no obligation to update publicly or otherwise revise any forward-looking statements whether as a result of new information or future events or otherwise, except as may be required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accept responsibility for the adequacy or accuracy of this press release.